Mayor Tom Ambrosino released the updated Capital Improvement Plan last week, and its entirety is available on the cityâ€s website (www.revere.org).
Among the highlights in the plan are the priorities for the street paving and sidewalk program.
This summer, crews will finish up work on the Revere Street neighborhood, including:
•Pomona Street
•Stowers Street
•Tuttle Street
•Shurtleff Street
•Hastings Street
•Neponset Street
•Carleton Street.
In the late summer, crews will start work on the Park Avenue side streets. The streets targeted include
•Irving Street
•Jarvis Street
•Kilburn Street
•Lambert Street
•Madison Street
•Newbury Street
•Oxford Street
•Howard Street
•Rand Street
•Dale Street
Outside of the target area, the following streets will be targeted for the next couple of years.
They are: Proctor Avenue (Broadway to Vivien), Porter/Eliot, Morris Street, Liberty Avenue, Borden Street, Tapley Place/North Ave, Rice Avenue, Keayne Street, Vinal Street, Endicott Avenue, Olive Street, Fenley Street, Newhall Street, Franklin Avenue, Centennial Avenue, Campbell Avenue, Tuscano Avenue and Beckert Street.
Target areas in fiscal year 2010 and beyond include Riverside, Point of Pines and Shirley Avenue.
The post Street Paving, sidewalks, etc. first appeared on Revere Journal.